Eagle-Acces software review

CompleXYS is hired by Elma to perform a review of the software they designed for the ‘Eagle Access’, an electrically driven offshore walk-to-work gangway, used as a personal and light cargo landing tool.

CompleXYS reviews and delivers a report with findings concerning program flow, overall quality of implemented code, possible programming errors and conformity with specified functional requirements.

Status: Completed

Alblasserdam NL, 14 January 2022

The new CompleXYS B.V. website is online!


We are proud to announce that the in-house developed new website of CompleXYS B.V. is online! On this website you can find all information about CompleXYS and its employees.


Alblasserdam NL, 3 December 2021

Automation for Hornet Laser cladding

CompleXYS B.V. provides the automation and commissioning of the Hornet Laser cladding machine for Innovative Industries.

Build for:
Status: Active

Alblasserdam NL, 26 October 2021

Automation for Hornet Laser cladding

CompleXYS provides the automation and commissioning of the Hornet Laser cladding machine for an undisclosed customer.

Status: Active

Alblasserdam NL, 26 October 2021

CompleXYS B.V. & Huisman equipment are going to work together on the new series of Leg Encircling Cranes!

CompleXYS B.V. supports Huisman with the development of the series Leg Encircling Cranes to be installed on various new build Wind Turbine Installation Vessels.

Huisman LECs are characterised by their lightweight, yet robust crane designs, with a high level of reliability, positioning accuracy and energy efficiency, making them ideal for the construction of offshore wind farms.

Status: Active

Schiedam NL, 14 july 2021

Modification of the Rent-All warehouse installation

CompleXYS B.V. adjusted the system of Rent-All's automated warehouse in Bemmel.

Build for:
Status: Completed

Bemmel NL, 13 July 2021

Automation & Commissioning

CompleXYS B.V. is developing, implementing and testing software for multiple projects for MSA-Service B.V.

Status: Active


Hardinxveld-Giessendam NL, 01 March 2021

2021

Commissioning support for the Seven vega reel-lay system

CompleXYS B.V. supporting IHC during the commissioning of the Reel-Lay system on the Seven Vega vessel.

Seven Vega reel-lay vessel design

The Seven Vega reel-lay vessel will be 149.2m-long and 13m-deep with a breadth of 33m and draught of 8.3m.

Seven Vega pipelay systems

The vessel will be installed with two reels with a 5,600 ton storage capacity main reel and a secondary reel with a capacity of 1,600ton. It will have a maximum dynamic top tension capacity of 600 ton.

The pipelay systems will be able to install pipeline end terminations (PLETs) measuring 5mx5mx10m. The vessel will also be fitted with abandonment & recovery winches.

Build for:
Status: Completed

Schiedam NL, 25 May 2020

The Voltaire, ready for the future of the renewable energy market!

CompleXYS B.V. & Huisman equipment are working together on the powermanagement & the development of the Quick Connector for the Van Oord Voltaire Huisman crane.

The Voltaire is specifically designed to transport, lift and install offshore wind turbines, transition pieces and foundations for current and future developments. The vessel will have better operational limits compared to the existing Jack-Up installation vessels. Not only will this vessel be ready for the future of offshore renewables, it will also be deployable for the oil and gas industry, and for decommissioning of offshore structures. All these activities will be performed in a sustainable way thanks to lower fuel consumptions and emissions through Jan De Nul’s in house developed ULEv technique (Ultra Low Emission vessel).

The Voltaire is equipped with a main crane of over 3,000 tonnes and a DP2 system. The vessel has an operating depth of over 80 meters, a payload of about 14,000 tonnes and accommodation for 110 persons. With her four legs, the Voltaire can lift itself above the sea level for stable working conditions.

Build for:
Status: Active

Schiedam NL, 03 February 2020

Les Alizés, A crane like the world has never seen before!

CompleXYS B.V. is providing conception, engineering, building, commissioning & support for Les Alizés a state of the art vessel with Huisman equipment crane.

Les Alizés will be ready in 2022. Les Alizés is equipped with a crane having a lifting capacity of 5,000 tons and equally impressive lifting heights. The Vessel will mainly be used for the construction of offshore wind farms, but with her impressive crane she is also extremely suitable for decommissioning offshore oil and gas platforms.

Thanks to her dimensions and impressive lifting and loading capacities, Les Alizés will be able to load out, transport and install multiple units of the largest and heaviest wind turbine foundations. In addition, as a crane vessel that floats, it will be able to install heavier and larger foundations into deeper waters and in more challenging seabed conditions.

Build for:
Status: Active

Schiedam NL, 03 February 2020

2020

Together we train the next generation of professionals!

CompleXYS B.V. is now an accredited training company by S-BB. Students receive the best possible practical training with prospects of a job, and companies can employ professionals that they need, now and in the future. These are the objectives of the Foundation for Cooperation on Vocational Education, Training and Labour Market (SBB).

We recognize and guide the training companies where students, workers and job seekers can go for an internship. And we make agreements about what the student needs to know and be able to do in order to achieve for example their MBO Certificate (post-secondary vocational education).

CompleXYS B.V. is proud of this accreditation, we look forward to training the next generation of professionals together!

Alblasserdam NL, 6 November 2019

CompleXYS B.V. supports the Future!

CompleXYS B.V is providing automation support to Pat Kruger for the development of the Mammoet FOCUS30 crane of the future!

rawler cranes often need to be erected above live areas of the plant, putting workers and key infrastructure at additional risk. As it can take up to four weeks for these cranes to become operational, scheduling can be severely affected.

The FOCUS30 helps with a fast and safe project in several ways.

The FOCUS30 improves productivity by freeing up space on site. Its boom mast is assembled vertically in sections, allowing the assembly to take place from just a 30x40m footprint.

Besides that it allows projects to start and finish sooner. The FOCUS30 can be assembled within 10-14 days and can be transported to the lift position in smaller, more maneuverable pieces.

Also reduces the FOCUS30 project risk. Boom erection does not overhang adjacent areas of the plant, so plant workers, pipe racks and other key infrastructure can operate more safely. The FOCUS30 is a 2,500t class crane, and so is ideal for a wide range of lifts, while its minimum 6t/m2 ground bearing pressure means it can operate at a wider range of sites.

Build for:
Status: Completed FOCUS30

's-Hertogenbosch NL, 23 Ocotber 2019

Servicing Aeolus

CompleXYS B.V. conducted a post-delivery examination & resolved warranty items on the Van Oord Aeolus.

Build for:
Status: Completed

Maasvlakte 2 NL, 27 September 2019

CompleXYS B.V. Builds a digital Twin

CompleXYS B.V. is providing a 'state-of-the-art' digital twin of the automated Rent-All warehouse in Bemmel.

Bemmel NL, 27 August 2019

CompleXYS and Reesink teaming up again!

CompleXYS B.V. is providing the automation & commissioning for the Rent-All automatic warehouse. This warehouse is build by Reesink Logistic Solutions B.V.

Build for:
Status: Completed

Bemmel NL, 27 August 2019

General installation & commissioning support

CompleXYS B.V. is providing commissioning & installation support to the T-Car system of Reesink Logistic Solutions B.V.

Build for:
Status: Completed

Dordrecht NL, 16 July 2019

T-Car Commissioning

CompleXYS B.V. is providing the commissioning for the T-Car system of Reesink Logistic Solutions B.V. at B&S

Build for:
Status: Completed

Dordrecht NL, 14 February 2019

2019

Webshop build for LotSaFun

CompleXYS B.V. is providing the Magento 2 webshop, PHP/Java modules and design for LotSaFun B.V.

Build with:
Status: Completed


Alblasserdam NL, 14 December 2018

Enlarging capabilities!

CompleXYS B.V. is teaming up with our good friends at Stellio to strengthen their industrial automation and support capabilities.

Build for:
Status: Completed

Alblasserdam NL, 14 October 2018

First Birthday!

CompleXYS B.V. is celebrating it's first birthday! With thanks to our families, all our clients and supporters who stood along side us.





Alblasserdam NL, 2 October 2018

Automation support for the Pioneering Spirit

CompleXYS B.V. is teaming up with Louter Control & EPMC to deliver the constant tension control on the EPMC crane tuggers for the Heerema Pioneering Spirit.

Build for:
Status: Completed

Alblasserdam NL, 12 June 2018

Vessel Automation for the newbuild vessel 'Orion'.

CompleXYS B.V. is pleased to announce another project together with Bakker Sliedrecht and YER! Together we will provide the vessel automation for the DEME newbuild DP3 vessel 'Orion'.

Build for:
Status: Completed

Sliedrecht NL, 29 January 2018

2018

Automation upgrades to the Van Oord Stornes

CompleXYS B.V. successfully completes the automation upgrades for the Van Oord flexible fallpipe vessel Stornes and implements the Deep Excavation System. Check out the stunning FFPV Stornes system animation below and the introduction movie here.

Build for:
Status: Completed

Sliedrecht NL, 9 November 2017

First CompleXYS B.V. job completed!

CompleXYS B.V. completes its first job onboard cruise ship MV Le Lyrial (Ponant).

Build for:
Status: Completed

27 October 2017

One of the award winners!

CompleXYS B.V. director Joël Smit was honoured to be selected amongst the 2016 "Engineering Leaders Under 40" award winners by a jury of CFE Media-publisher of Control Engineering and Plant Engineering magazines-and their subscribers.

"The Engineering Leaders Under 40 program recognizes manufacturing professionals under the age of 40 who are making a significant contribution to their plant’s success, and to the control engineering and/or plant engineering professions. Our research shows that finding, training and retaining workers is the biggest issue facing manufacturing today. The goal of the Engineering Leaders Under 40 program is to call attention to these successful young engineers in manufacturing and to show how manufacturers are recruiting and developing the next generation of manufacturing professionals."

Chicago USA, 3 April 2017

Start CompleXYS B.V.

Joël Smit has founded CompleXYS B.V.





Alblasserdam NL, 2 October 2017